Our Events

  • November 09, 2009
    Incorporated under Companies Act, 1956 as “ Waa Solar Private Limited ”.
  • January 09, 2010
    The Company was acquired by Madhav Power Private Limited, a Madhav Group Company
  • May 21, 2010
    10 MW Power Purchase Agreement executed between Company & Gujarat Urja Vikas Nigam Limited (GUVNL) for Solar Power Plants at Village: Nayka, Tal. Sami, Dist. Patan in Gujarat
  • October 08, 2010
    Supplemental Power Purchase Agreement executed between Company & Gujarat Urja Vikas Nigam Limited (GUVNL) for Solar Power Plants at Village: Tikar, Tal. Muli, Dist. Surendranagar in Gujarat.
  • February 27, 2012
    Certificate of Commissioning received from Gujarat Energy Development Authority for Commissioned 10.25 MW capacity Solar Photovoltaic Power Project
  • January 30, 2013
    100 KW Power Purchase Agreement executed between Company & Airport Authority of India for Solar Power Plants at Raja Bhoj Airport, Bhopal
  • June 28, 2013
    Certificate of Commissioning received from Airport Authority of India for Commissioned 100 KW capacity Solar Photovoltaic Power Project.
  • February 19, 2018
    Converted in to a Public Limited from Private Limited